Component |
Hospitals |
Buildings Detailed Cost Estimate in INR Crores |
Tender Amount |
Status |
---|---|---|---|---|
1 |
Government Hospital Avadi, Thiruvallur |
26.90 |
28.53 |
Foundation Work is 100% completed, basement work is 100% completed. Super structure work commenced. |
2 |
Government Hospital Velampalayam, Tiruppur |
27.00 |
28.75 |
Foundation Work is in progress, earth work excavation 85% completed next footing work will be commenced. |
3 |
Government Hospital Ammapet, Salem |
26.70 |
28.46 |
Site Clearance work under progress, foundation Work will be started after site Clearance. |
4 |
Government Hospital Kandiyaperi, Tirunelveli |
28.90 |
31.29 |
Foundation Work is in progress expected to be completed by 15.08.2021 |
Total | 109.50 | 117.03 |
Administrative and Financial sanction of Rs. 109.50 crores obtained in GO (Ms) No: 80 Health and Family Welfare (EAP II – 1) Department, dt: 05.03.2020. Contract agreement for constructions multi – storey building signed on 19.04.2021 and construction work is in progress. The construction work at all four sites is expected to be completed by September 2022.
Component |
Hospitals |
Equipment cost as per DPR in INR Crores Tenders will be called for and procured |
---|---|---|
1 |
Government Hospital Avadi, Thiruvallur |
12.86 |
2 |
Government Hospital Velampalayam, Tiruppur |
12.86 |
3 |
Government Hospital Ammapet, Salem |
12.86 |
4 |
Government Hospital Kandiyaperi, Tirunelveli |
12.86 |
Total | 51.44 |
The list and specification was vetted by TNMSC, this will be shared to JICA for concurrence by 3rd week of July. After obtaining JICA concurrence, it will be placed in SEC committee.
August 2021 | September 2021 |
---|---|
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (dt. 01.08.2021) |
Shuttering work completed for ground floor roof level. (dt. 02.09.2021) |
Project Director & JICA Representative - Site Visited on 02.08.2021 |
Mr. Duglus, AEE, PWD visited site and inspected the Electrical lines and conduits fixed in ground floor roof slab before pouring concrete. (dt. 09.09.2021) |
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021) |
Reinforcement and shuttering supports for roof slab work inspected consultant and PWD officials. (dt. 09.09.2021) |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 14.08.2021) |
Completed Ground floor roof slab concrete works. (dt. 15.09.2021) |
SE & AEE (Electrical), PWD visited the site for monitoring quality and progress of construction works. (dt. 23.08.2021) |
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 17.09.2021) |
AEE (Electrical), PWD & AE (Electrical), PWD visited the site for joint inspection. (dt. 28.08.2021) |
SE-PWD, EE-PWD, AEE – PWD visited site for general inspection of work progress. (dt. 29.09.2021) |
De-shuttering the columns and covered by gunny bags for curing Dt. 05.08.2021 |
Preparation and fixing ramp column box for column lifting up to ground floor roof beam bottom level Dt. 02.09.2021 |
Column concrete works under progress Dt. 07.08.2021 |
Reinforcement cutting, bending and laying for ground floor roof slab in lobby area Dt. 09.09.2021 |
Shuttering for mid landing beam under progress Dt. 13.08.2021 |
Pouring RCC concrete for ground floor roof beam, slab, Staircase flight 3 and Ramp flight up to first floor level. Dt. 14.09.2021 |
Made centring plates for staircase and laying for staircase slab Dt. 17.08.2021 |
Curing the completed columns, staircase flight 1, 2 & 3, ramp 1 & 2 flight and Ground floor roof beam and slab Dt. 20.09.2021 |
August 2021 | September 2021 |
---|---|
Concrete pouring on footings completed. (dt. 02.08.2021 |
PWD Executive engineer general site visit and inspected Footing reinforcement works. (dt. 08.09.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (Dt. 04.08.2021. |
Footings level concrete completed. (dt. 11.09.2021) |
Quality Control team, PWD visited the site for monitoring quality and progress of construction works. (dt. 06.08.2021) |
As per the agreement conditions, Environmental tests taken 1. Ambient air quality test 2. Ambient noise level test 3. DG Static emission test. (dt. 14.09.2021) |
Discussion with AE, PWD & Nodal Officer. (dt. 13.08.2021) |
Newly posted Executive engineer & Assistant Executive engineers, PWD visited the site. (dt. 18.09.2021) |
Detailed project display boards in Tamil & English language are provided in the site. (Dt. 14.08.2021) |
Discussion points are : 1. Personal protective equipments 2. Workers welfare facilities 3. Job hazards and precautions. (dt. 11.09.2021) |
Safety meeting conducted by the Consultants for the site labours. (dt. 26.08.2021) |
Safety training conducted by safety engineer for workers & supervisors 1.Fire fighting training. 2.Manual handling and material shifting. (dt. 28.09.2021) |
PWD quality control EE, AEE,AE visited the site. Some instructions given to the contractors to follow up. (dt. 27.09.2021) |
Work progress as on August 2021 | Work progress as on September 2021 |
---|---|
Shuttering work for Footing Dt. 02.08.2021 |
Footing marking with total station Dt. 01.09.2021 |
UG sump base slab reinforcement work under progress Dt. 05.08.2021 |
Raft footing bottom mat under progress Dt. 07.09.2021 |
Hard rock strata removal from foundation areas under progress Dt. 11.08.2021 |
RCC concrete pouring for footings (M25 Grade) CF6, F6, F8, F1, CF5, F3, F3, RF8 Completed Dt. 11.09.2021 |
UG static water tank with pump house wall shuttering work under progress Dt. 20.08.2021 |
Grade beam shuttering work under progress Dt. 18.09.2021 |
Existing Building demolition work and Excavation work under progress Dt. 24.08.2021 |
Curing work for all concrete surface under progress Dt. 23.09.2021 |
Bar bending and rebar binding work for footing under progress Dt. 28.08.2021 |
Grade beam pouring concrete work under progress Dt. 27.09.2021 |
|
|
August 2021 | September 2021 |
---|---|
Joint Site Inspection with DTCP Joint Director, PWD, Consultants & Contractor on 05.08.2021 |
Earth backfilling and consolidation work started on 01.09.2021 |
Grade concrete pouring work has been completed on 10.08.2021. |
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 02.09.2021) |
EE, PWD visited the site for monitoring quality and progress of construction works. (dt. 13.08.2021) |
Ramp area Ist flight slab reinforcement work under progress. (dt. 03.09.2021) |
Environment upgradation activity: 21 numbers of trees are planted at hospital campus. (dt. 13.08.2021) |
Flooring P.C.C. work & HUME pipe laying work has been started on 06.09.2021. |
CE, PWD visited the site for monitoring quality and progress of construction works. (Dt. 14.08.2021). |
Consultant team combining DTL, MEP Engineers has visited the site and discussed with PWD execution team / Contractor for MEP. (dt. 08.09.2021) |
75th Independence Day celebrated at the construction site. (dt. 15.08.2021) |
The new EE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 18.09.2021) |
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (dt. 21.08.2021) |
Meeting held with PWD, PMC & Contractor to expedite the ground floor slab concreting. (dt. 23.09.2021) |
Site inspection by AEE, PWD on 25.08.2021 |
Verifying of ground floor roof slab reinforcement work under progress. (dt. 24.09.2021) |
New PWD S.E. Er. Sathyamoorthi visit our site and he has planted trees in our site campus and we are held test for Fly ash brick in presence of SE. Test result for fly ash brick 8.65N/mm2 on 28.08.2021. |
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 30.09.2021) |
Work progress as on August 2021 | Work progress as on September 2021 |
---|---|
Grade beam pouring concrete work under progress Dt. 01.08.2021 |
Gravel filling and water consolidation work onbasement wall constructed areas Dt. 02.09.2021 |
Steel reinforcement has been checked and Concrete pouring work for grade beam under progressDt. 07.08.2021 |
Hume laying work for rain water and sewage waterfrom O.T.S to building outside Dt. 09.09.2021 |
Excavated earth back filling up to grade beam incompleted areasunder progress Dt. 11.08.2021 |
Concrete pouring work for staircase first waist slaband landing Dt. 13.09.2021 |
Brick work for basement walls up to DPC level work under progressDt. 19.08.2021 |
Steel rods hoisting, placing & binding work for groundfloor roof beams as grid X-axis 1 to 13, Y-axis 10 to 16 Dt. 20.09.2021 |
Gravel filling work on basement wall constructed areas under progress Dt. 24.08.2021 |
Form work for ground floor roof slab work under progress Dt. 23.09.2021 |
Concrete pouring work for column lift up to roof levelas grid X-axis 11 to 15, Y-axis 1.2 to 2.1work under progressDt. 31.08.2021 |
Reinforcement work under progress Dt. 29.09.2021 |